People's Democracy(Weekly Organ of the Communist Party of India (Marxist) |
Vol. XXXV
No. 48 November 27, 2011 |
Nuclear
Liability Act & its Rules:
The
Tail Wagging the Dog
Prabir
Purkayastha
THE
Civil Liability for Nuclear Damages Rules notified on November
11, 2011 does
what the
The
timing of it is also equally important. Hillary Clinton came
in July 2011 and
ticked off the Indian government that if they wanted to
continue with the
special relations with the
KEY ELEMENTS
NULLIFIED
What
are the key elements in the Civil Liability for Nuclear
Damages Act that have
now been virtually nullified by the Rules? The Act clearly
laid down the
provision of a right to recourse by the nuclear operator in
the article 17 of
the Act. If there was an accident and the operator was held
liable for damages,
he could recover the damages from the supplier provided he
could show that the
accident was due to defective supplies or services. This is
what the nuclear
suppliers from the
What
has now been done is to nullify Article 17 of the Act in THREE
different ways.
One is what has already been high-lighted in the media reports
– the right to
recourse has been restricted to either the period of granting
of initial
license or the product liability period, whichever is longer.
Normally, a
product liability period is a standard warranty period,
generally of 12 months
after commissioning of the plant. The initial license period
is again generally
of five years duration.
Normally,
an operator will have to secure a license before he can start
construction.
Since the plant construction takes more than five years, the
initial license
period would have expired even before a nuclear plant is
commissioned. So with
this clause, the government has effectively limited the period
of recourse only
to the warranty period. If an accident takes place after 12
months, the
supplier will then have no liability.
The
other three clauses all limit the amount of liability. The
clause 24 of the
Rules state that the amount of liability in the right to
recourse will be up to
the operator's liability if this is provided explicitly in the
contract or the
value of the contract, whichever is less. As the
contractor will not
agree – given this choice – of including such a liability in
his contract, this
effectively limits the liability only to the value of the
contract.
The
key issue here is that all liability regimes carry what are
known as
consequential damages. This is the position in Indian law as
well. If by your
action you have caused damage to persons or the environment,
you are liable for
the full value of the damages. There is no restriction that
the damages are
limited only to the value of your contract or investment. By
limiting the
amount to the value of the contract, all consequential
liability as exists
under the current liability regime and even under the original
Liability Act is
being removed.
The
third way that liability is being diluted is vide explanation
2 to Clause 24 of
the Rules, the operator's claim shall in no case exceed the
actual amount of
compensation paid by him up to the date of filing such claim.
This is quite
preposterous as a rule. By this clause, the accident has to
take place, the
compensation claim would have to be filed by the victims,
should be settled and
paid by the operator, all within the first 12 months of the
operation of the
plant, if the operator has to exercise his right to recourse.
This is as good
as no recourse at all!
In
any case, the total claim of the operator under this right to
recourse in the
original Act would not have exceeded Rs 1500 crore as this is
the limit of the
operator's liability. Any damages beyond this are to be borne
by the government
– this is the weakness in the Liability Act itself. We had
pointed out when the
law was passed that this was a very weak liability regime as
the damages from a
nuclear accident are in billions. The bill for the
Why
is
liability important in supply of all products? The simple
issue is that if
there is no liability regime, companies can supply
sub-standard material with
impunity. The liability regime that has evolved in law is
precisely to prevent
such behaviour by rapacious private capital. By limiting
liability in this way,
the Indian government is giving a carte blanche to
nuclear suppliers to
play with the safety of the Indian people.
When
the Liability Act was being discussed in the standing
committee of the
parliament, all these clauses were examined in details. A
number of attempts
were made by the ruling party MP's including the chairman of
the committee,
Subirami Reddy to water down the
right
to recourse and limit it to the warranty period or only if it
was explicitly
included in the contract. Both these were rejected by the
parliament. So the
legislative intent has been clearly violated by the UPA
government – the Rules
notified are substantive changes to the content of the
legislation and are
clearly illegal.
TOO CLEVER
BY HALF
The
viability of nuclear energy is closely connected to its cost.
And one of the
costs is the hazard it poses. Amongst all hazardous
industries, the nuclear
equipment industry is the only one that argues that it should
carry no
liability for hazards. This is because it perceives the risk
to be too high of
such an accident, while claiming in public that the risks of a
nuclear accident
are very low.
I
do not believe unlike some of my friends that nuclear energy
cannot be made reasonably
safe. However, there is a cost associated with making nuclear
energy reasonably
safe. It is this cost that the nuclear industry does not want
to pay. This is
why the chorus of the
The
costs of nuclear energy have risen continuously. Contrary to
public opinion,
nuclear energy did not get killed in the west due to accidents
such as Three
Mile Island or
The
reactors being built today, the two Areva reactors – one in
This
UPA government has now a well-earned reputation of being too
clever by half. It
believes that as it has a clever bunch of lawyers within the
union cabinet,
they can draft things in legalese which people are too
dumb to
understand. The problem is that fooling the people is not
possible all the time
– it finally catches up. And this is what is increasingly
happening to the UPA.
Even
the very limited liability that the Liability Act passed by
the Parliament has
been virtually thrown away to please the US and its nuclear
industry, even
though the US has reneged on its own commitments – fuel
enrichment and other
dual use technology will not be available to India. That even
after Fukushima,
the Indian government with its own memories of Bhopal would
play with safety of
nuclear plants is criminal.
The Indian parliament
should assert its will and reject this violation of the
Liability Act through
this travesty of Rules.