People's Democracy(Weekly Organ of the Communist Party of India (Marxist) |
Vol. XXXV
No.
38 September 18, 2011 |
CAG
REPORT ON KG BASIN GAS
A
Damning Indictment
of
Govt and Reliance
Prabir
Purkayastha
THE
CAG Report on the audit of the Production Sharing Contracts for the
on-shore
and off-shore oil and gas blocks once again shows the unholy nexus
between the
UPA and big capital in the country. The CAG has shown how the
Directorate
General of Hydrocarbons (DGH) and the Ministry of Petroleum and Natural
Gas
(MoPNG) connived with Reliance Industries Limited and other private
operators
against the interests of the people. Some of the salient issues brought
out by
CAG are:
·
Private operators grossly
inflating the capital costs for equipment to claim a much higher share
of the
profit petroleum
·
In procurement of equipment, a
number of one party financial bids, major revision of
scope/quantities/specifications, substantial variation in order
quantities,
post bid modifications in major high value contracts
·
Allowing the whole 7645 sq km
exploration area to be retained by Reliance instead of their
entitlement of
retaining only 5 per cent of this area after 2009 in complete violation
of the
Production Sharing Contract.
There
has been some criticism that CAG's draft report has been diluted in the
final
report. This is not borne out by facts. CAG's language might become a
little softer,
but its conclusions remain essentially unchanged.
A
major part of the report is devoted to the KG Basin – KG-DWN-98/3
deep-water
Block, also known as KG D-6 Block. Reliance has argued that the
increase of
capital cost from $2.4 billion to $8.8 billion was for augmenting gas
field
output from 40 mmscmd to 80 mmscmd. The CAG Report now makes clear that
the
increase from $2.4 billion to $5.2 billion took place for the first
phase
itself, where no augmentation of capacity was involved.
It
is important to note that the evaluation of bids that were made for the
award
of the exploration blocks is linked to the financial packages that the
bidders
offered. As the profit share and other measures promised by the bidders
in the
financial package are linked to capital costs, this huge change in
capital
costs makes nonsense of the bidding procedure for awarding of blocks.
Worse
is the timing of the approvals. The original cost estimates of $2.4
billion was
a part of the Initial Development Plan (IDP) submitted by Reliance in
May 2004.
In October 2006, Reliance submitted an Addendum to the IDP for an
upward
revision of the costs to $5.2 billion for the first phase and another
$3.6
billion for the second phase – a whopping increase of $6.2 billion
over the
original estimate. The Management Committee which had 50 per cent
representation from the government cleared this increase by December
12, 2006 –
in a period of less than 2 months!
SWEET-HEART
DEALS
TO AKER
In a single party financial bid, a contract of $1.1
billion
was given to Aker Floating Production, a part of the Aker group for a
10-year
lease on a Floating Production and Storage and Offloading (FPSO)
Vessel.
Another contract of $200 million for O&M services was also given to
Aker
for the same FPSO. This was originally budgeted for $300 million. All
other
bidders were disqualified and only Aker's financial bid was opened.
CAG has also pointed out the following with respect to
the
Aker's above contract:
ń
Aker did not meet the
requirements of the specifications with respect to its experience in
such
contracts
ń
Its financial bid was not
signed and should not have been considered
ń
It was allowed to make post
technical bid modifications – an opportunity not given to the other
bidders
ń
Aker had bought two oil tankers
for $55 million and the conversion cost of the two tankers to FPSO by
Jurong
Shipyard was $88 million.
The
CAG Report has pointed out 8 contracts were given to Aker group out of
10
single party bids on what appears prima facie to be sweet-heart
deals.
CAG has rejected Reliance's claims that its procurement procedures
cannot be
subjected to CAG audit and stated that it is going to examine these
issues in
greater detail in a subsequent audit.
The issue of high capital cost is not merely that of
skimming off the top by incurring fictitious or inflated capital
expenditure.
It changes the revenue share between the private party and the
government
completely. The Investment Multiple to which profits of GoI and private
parties
are indexed, is the ratio of the cumulative net cash income to the
cumulative
exploration and development costs – it is a measure of the capital
intensive
nature of the project. CAG has pointed out, “The slabs for profit
sharing are
so designed that more capital expensive the project (i.e. lower IM),
the lower
the GoI's share of the “profit petroleum” (which could be as low as
5-10 per
cent). Contrarily, the higher the IM (i.e. less capital intensive
vis-a-vis the
income) higher the GoI's share of the profit petroleum (which could be
as high
as 85 per cent).”
NOT VALID
EXPENDITURE
Recent press reports indicate that Reliance's basis of
capital cost increase – augmenting gas flow from 40 mmscmd to 80 mmscmd
has
fallen far short of its promise – the gas output is now well below 60
mmscmd.
The Solicitor General has given his opinion – as per news reports –
that GoI's
profit share should not be reduced due to this capital expenditure as prima
facie this is not a valid expenditure.
The CAG report has also given a chart of the receipts of
the
GoI from royalties and profit petroleum during the period 2005-06 to
2010-2011.
It shows that while royalties have been rising steadily showing an
increase in
oil production from the Production Sharing Contracts, the receipt from
profit
petroleum falls abruptly from Rs 5,926 crore in 2009-2010 to Rs 3,610
in
2010-2011. This is in spite of an increase of royalties showing clearly
that
output in this period has physically increased. While CAG has given no
explanation for this, it is clear that all is not well with the NELP
and the
Production Sharing Contracts with private parties.
RELIANCE'S
TENTACLES
In
November 2009, preliminary investigations by the CBI had found evidence
of
“gross abuse and misuse of public office” by V K Sibal, the then
Director
General of DGH. This had been informed to the petroleum ministry and to
CVC.
Numerous links had been found between Sibal and Reliance. The CBI
enquiry
remains stalled, very much in the telecom 2G mode, showing that
Reliance
tentacles in the government go far beyond Sibal.
Apart
from the major scam of gold-plating of contracts, the other major issue
is that
DGH and Ministry connived with Reliance so that it could “hoard” the
entire
exploration area as discovery area. As per the Production Sharing
Contract,
Reliance was supposed to vacate 25 per cent of the exploration area in
the
first phase, 50 per cent in the second phase and all areas in which it
had not
sunk wells or developed oil wells in the third phase. Instead, Reliance
never
relinquished any of the areas and has been allowed to keep all 100 per
cent of
the 7645 sq km of the exploration area in complete violation of the
contract.
If
any company takes a particular area for exploration, it must finish the
exploration within a certain time period or release it back to
government for
awarding it to others. It cannot sit on top of an exploration area and
hoard it
indefinitely for the future. That is why the clause of progressive
release of
exploration areas back to the government.
Normally, when gas or oil is struck in an area, its
nearby
areas are also likely to have hydrocarbon deposits. The value of such
areas
would therefore go up for any subsequent auction. Hoarding such areas
means
that though the party considered has not spent the money it was
required for
exploration, it is still allowed to retain this area and explore it at
leisure.
The entire purpose of NELP of time bound and expeditious development of
The Panna Mukta oilfield and the one held by Cairn Energy
shows similar features to the KG DWN 98/3 Block issues. This brings
into
question the entire New Exploration Policy and the way it is being
implemented
by MoPNG and DGH. CAG report has also brought how Reliance and other
contractors have flouted various contract terms and conditions, how it
has
incurred expenditure without approvals, did not submit required plans
and
documents, etc. The major issues it has raised is the way that the
government
has supervised the production sharing contracts. It has also suggested
that a
far simpler scheme would be to peg government's stake simply on the
output –
this way no complex mechanism needs to be put in place for monitoring
the
contracts and the purchases. For existing contracts, where a profit
sharing
arrangement is in place, the government has to exercise far greater
vigilance
than it has shown till now to protects its revenues.
Both DGH and PoNG have clearly connived with Reliance and
the private operators. CAG has also made an observation that DGH has to
separate its two roles – one as a technical advisor to the MoPNG the
other as a
regulatory body. The key issue is however not that of separation of
roles as
much as playing the role it was designed to do – safeguard the
interests of the
people in the production sharing contracts. This, it has clearly failed
to do.
Various other criticisms have been mounted against CAG –
one
by Congress MPs in parliament and echoed by others outside – that CAG
is going
beyond its role of audit into policies. In this case, CAG has examined
only
those which pertain to GoI's revenues share being reduced.
Unfortunately, today
policies are being crafted in a way to suit private interests and
against
public good. Both 2G spectrum allocation and the NELP are policies
which have
benefited private parties to the detriment of public good.
There are two sets of issues that need to be addressed
urgently. One is that immediate measures need to be taken to vis-a-vis
Reliance
and other private parties. These include:
ń
Taking back 95 per cent of the
exploration area retained by Reliance in gross violation of the
Production
Sharing Contract
·
Imposing penalties on Reliance
and other private parties for gold-plating
contracts
·
Ensuring that such increase
is considered
invalid expenditure such that GoI's
share of the profit petroleum is not reduced
For the government, the following steps need to be taken
so
that a repeat of this does not take place again:
·
Immediate prosecution of Sibal
and other concerned officials
·
Investigation of the role of
ministry of petroleum and the erstwhile petroleum minister in this
·
Strengthening the role of the
government in the management committee for the existing contracts
·
Change in Production Sharing
Contracts to prevent such misuse
·
Review of the NELP