People's Democracy(Weekly Organ of the Communist Party of India (Marxist) |
Vol. XXXV
No.
37 September 11, 2011 |
KG Basin: How
Govt Allows Daylight
Robbery
S R Paranjpe
THE
Comptroller & Auditor General of India (CAG) has already submitted
its
draft inquiry report into the dealings of the ministry of petroleum and
natural
gas (hereafter, MPNG) with three contractors, namely the Reliance
Industries
Ltd (RIL), Cairn India and British Gas --- in connection with the
production of
crude oil and natural gas from the Krishna Godavari Basin (KG Basin)
and other
areas. Now it is learnt that the CAG is in the process of finalising
its
report, and it is understood that the final report would be placed
before the
parliament soon. It is in this background that we venture to make the
following
submission for consideration by one and all, in response to some
comments that have
appeared in public domain on behalf of the MPNG and in defence of the
RIL’s
inflated cost for KG Basin block.
LAME-DUCK
DEFENCE
One
of these comments says that the increased capital cost is the result of
increased production capacity from 40 to 80 million standard cubic feet
per day
(mscfd) but that the CAG did not take into account the increased
production
capacity while making its comment. The government had earlier approved
a capital
expenditure of 2.47 billion dollars to explore 5 trillion cubic feet
(tcf) of
gas at 40 mscfd, which was then increased up to 8.8 billion dollars to
explore
10 tcf gas at the production capacity of 80 mscfd. Thus the increase in
capital
expenditure is 3.5 times for an increase in gas production by 2 times,
which is
highly disproportionate. The economy of scale is a well proved theory
and applies
in every sector, and there is no reason why the RIL’s KG block should
be an exception
to this theory. This disproportionate increase in the capital
expenditure,
which is popularly known as “gold plating” of the approved capital
expenditure,
brings out the collusive nexus between the RIL of Mukesh Ambani and the
government
of
We
have at hand a copy of the quarterly progress report submitted by the
RIL to
the ministry, giving the details of the expenditure on exploration and
development of the production wells up to March 31, 2009. The report
also gives
the details of the expenditure on exploration, development of the wells
and
production cost incurred during the period April 1 to June 30, 2009. It
may be
recalled that the production of natural gas in the KG Basin began in
April 2009
while the production of crude oil began from June 2009.
Extrapolation of these data to the end of the
fourth quarter, i.e. March 31, 2010, indicates that the total
expenditure on
exploration, development of the wells and production cost incurred
would have
been less than 8.8 billion dollars. Therefore, to claim a capital
expenditure
of 8.8 billion dollars amounts to “gold plating.”
The
ministry has also said that an increase in the capital expenditure
(capex) did
not cause any financial burden on the exchequer. This
again is another crucial half-truth. It
is true that the government of
In
this connection, the parliament too has to look into whether the
ministry
officials breached the privilege of the parliament by offering the
abovementioned
comments to the press before the report could be presented to the
parliament.
UNFAVOURABLE
TERMS
FOR GOVT
It
is understood that some kind of competitive bidding was adopted for
award of
each of the blocks and that the RIL won the KG-D6 block through
competitive
bidding. But at each stage of the utilisation of natural gas, the RIL’s
share in
the profit is higher than the GoI’s share. While the GoI’s share of
profit is a
mere 10 per cent in the first stage and it is scheduled to rise to 85
per cent
in the last stage, there is a chance that this share may never reach
the 85 per
cent level due to the uncertain nature of the crude oil and natural gas
reserves. Moreover, even if that stage is reached, the cumulative share
of the RIL
in the profit would still remain higher that the GoI’s. Taking into
account the
fact that the product sharing contract (PSC) between the RIL and the
GoI is
only one contract out of 220 contracts of a similar type, it is
reasonable to
assume that many blocks have been awarded on terms that are more or
equally
unfavourable to the GoI. Such contracts, while being unfavourable to
the GoI, also
result in a concentration of wealth in the hands of a few contractors,
which is
against the letter and spirit of articles 39(b) and (c) of the
constitution of
India.
It
is thus clear that if the loss due to one such single contract is in
the range
of 100 million dollars, then the loss for 220 such contracts would run
into
thousands of millions of dollars.
This
also means that the new exploration and license policy (NELP), under
which all
these contracts were signed, allows undue benefits to private
developers of the
natural resources of our country and needs to be urgently reviewed.
There is no
reason why the NELP should deviate from the “normative cost plus”
methodology
which has been effectively implemented in other sectors.
There
is still another aspect to it. International market prices are given in
case of
imported products, which implies utilisation of external resources. But
when
internal or our own resources are being utilised, there is no logic of
giving
the producers international prices as it amounts to granting them an
undue
share of internal natural resources. Thus there is no need of
mentioning the international
prices of crude oil and natural gas in these product sharing contracts.
UNJUSTIFIABLE
PRICE
OFFER
In
order to estimate the reasonable price for gas production, one may
suggest the
adoption of an equated monthly instalment (EMI) approach in which loan
is
repaid in equal monthly instalments covering the interest.
One
may estimate the expected price of gas production in KG D6 block by
assuming the
entire capital expenditure as loan with an interest rate of 8 per cent
for a
period of 10 years. The estimation also allows for an operations and
maintenance cost at 2.5 per cent. The gas prices with different capital
expenditures
are given in Table A alongside.
It
may be seen from the above table that, even with an inflated capex, the
expected price of the gas would come to around 2.47 dollars per million
British
thermal units (MMBTU or MBTU). Thus, offering a price of 4.2 dollars
per MMBTU
is in no way justifiable or explainable. It is therefore not surprising
that when
one E A Serma asked information about the same from the MPNG, he did
not
receive any reply or explanation about how it arrived at such a high
gas price.
It is evident that the gas price determined by the government needs to
be
reviewed, considering the production cost of gas with a reasonable
return for
the developer.
And
now we have the year-wise RIL’s share and the government’s share in
profit
petroleum for a period of 10 years for utilisation of 10 trillion cubic
feet of
gas. Table B alongside shows the two shares with the gas price of 4.2
dollars per
MMBTU.
The
table shows that if the inflated production cost is allowed, it would
notionally reduce the profits of the RIL and the GoI but in real terms
the RIL’s
profit will increase while the GoI’s profit will fall.
We
have also estimated the impact of gas price as a parameter on the RIL’s
share
and the government’s share in profit, with assumptions like 5 per cent
royalty,
a production cost of 230 million dollars per year and a production rate
of 80 mscfd
(Table C).
These
figures do tell us that all the product sharing contracts need to be
reviewed,
irrespective of whether it is a pre-NELP or a post-NELP contract. The
concept
of paying to the contractor internationally market determined prices
for our national
resources, including natural gas and crude oil, allows a producer an
increased
profit with a rise in the international prices of gas and crude oil.
Any such
concept needs to be replaced by an administered price mechanism (APM).
The
procurement price may be so fixed as to give a reasonable margin of
profit to
the contractor.
Further,
one single generation cannot be allowed to consume all the
non-renewable energy
resources, as the future generations too are stakeholders. A government
can be only
a trustee of the national resources and has the duty to safeguard the
national
interest by utilising its authority to correct any error made in the
past,
instead of taking the plea --- a la A
Raja --- that it is only following an existing policy.
Indeed
the country needs a specific policy for each of the non-renewable
natural
resources like iron ore, bauxite, manganese ore, chromium ore etc, and
we must
immediately stop all mineral exports when it is clear that the
available
resources cannot meet our internal requirement for the next hundred
years in
view of the growth of our own economy. It is only logical that
explorations
must be carried out with the highest priority so that the country’s
economic
development can be planned properly. But at the same time there should
be no hurry
to exploit and utilise these non-renewable resources as many product
sharing
contracts compel us to do. It appears that kickback expectations from
contractors are forcing us to go in for fast utilisation of existing
resources.
The real need of the hour is to cancel all product sharing contracts
which are
violative of the directive principles of the constitution. The members
of parliament
too have a duty to stop this daylight robbery.
TABLE A
Capex
|
Period
of Loan |
O
& M Cost |
Interest
Rate |
Production
Cost |
Gas
Price |
(Billion
$ ) |
(Years) |
(%
of Capex ) |
(%
) |
(Billion
$) |
($/MMBTU)
|
5 |
10 |
2.50 |
8 |
1.19 |
1.55 |
7 |
10 |
2.50 |
8 |
1.67 |
2.17 |
8.8 |
10 |
2.50 |
8 |
1.90 |
2.47 |
TABLE B
Gas
Price = |
4.2
$/MMBTU |
|
Capex
|
RIL
Share |
Govt
Share |
($
billion ) |
($
million) |
($
million) |
5 |
12712 |
16378 |
7 |
13572 |
13518 |
8.8 |
16051 |
9239 |
TABLE C
Case |
Rate |
NCF |
RIL
Profit |
|
Equivalent
Percentage Returns |
|
($/unit) |
($
million) |
($
million) |
A |
B |
1 |
2 |
1403 |
4712 |
30800 |
15.30 |
2 |
2.34 |
1797 |
8018 |
24200 |
33.10 |
3 |
2.5 |
1936 |
9089 |
22410 |
40.60 |
4 |
2.8 |
2196 |
11288 |
19800 |
57 |
5 |
3.2 |
542 |
13774 |
17600 |
78.20 |
6 |
3.6 |
2889 |
13040 |
15048 |
86.70 |
7 |
4 |
3236 |
15270 |
13552 |
112.70 |
8 |
4.2 |
3409 |
16051 |
12848 |
126.20 |
9 |
4.3 |
3495 |
16743 |
|
|
10 |
4.4 |
3582 |
15276 |
12100 |
126 |
11 |
4.5 |
3669 |
15856 |
11706 |
133 |