People's Democracy

(Weekly Organ of the Communist Party of India (Marxist)


Vol. XXXV

No. 25

June 19, 2011

The Reliance KG Gas Scam

 

Prabir Purkayastha

 

THE CAG draft report on the audit of the production sharing contracts for the onshore and offshore oil and gas blocks is now widely being circulated in the media, showing once again the unholy nexus between the UPA and big capital in the country. The CAG has shown that the Directorate General of Hydrocarbons (DGH) allowed Reliance Industries and other private operators to gold-plate the capital costs of the plant, allowing them to make huge profits. The production sharing contract pegged the profit share of the private operators and the government to something called an investment multiplier, which meant that higher the capital cost, the larger the share of the profits of the private parties.

 

INFLATING THE

CAPITAL COSTS

The capital costs in the KG Basin D-6 Block went up from 2.4 billion dollars in the initial contract to 8.5 billion dollars. This was the pattern followed in other gas and oil fields also, involving Reliance, Cairn Energy and others. In all this, the modus operandi was to submit a bid which shows a certain capital cost and, during the operation of the contract, inflate the capital cost by a huge amount with the connivance of DGH and the Ministry of Petroleum. The management committee, in which the government had 2 nominees out of 4, played no oversight role in such inflation of contracts.

 

For inflating the capital costs, the familiar route is of course over-invoice through sweetheart deals from “friendly” sub-contractors, sometimes even a Reliance family company. While the CAG has not computed the loss to the exchequer, it has held that the Government has suffered large losses on this account. It has also held that the production sharing contact being followed by the government of India has very little controls on the investment costs, unlike for example, Bangladesh, where the management committee which has 50 per cent government nominees as in India, has to approve any expenditure above 500,000 dollars.

 

The CAG draft report has also brought out that while the contract envisaged that if the company did not develop certain areas within the contracted area within the stipulated time, it should have been relinquished. Instead, the DGH and the Ministry of Petroleum allowed the whole area to be designated as “discovery area” in violation of the contract.

 

As we shall show below, there are two sets of scams that have taken place, with the CAG having looked at only one of them. One is of course various violations of the production sharing contract as pointed out by CAG; the second is the high price of Reliance gas --- 4.2 dollars per million BTU (MBTU) --- set in 2007  by the Empowered Group of Ministers headed by Pranab Mukherjee. Reliance itself admitted in the court case between it and the NTPC/Anil Ambani Group that its production cost was 1.43 dollars per MBTU. Reliance Industries Ltd (RIL) had initially agreed to supply gas at 2.34 dollars to both NTPC and Anil Ambani Group, which it subsequently reneged once the EGOM set the price at 4.2 dollars. It might be noted that by its own calculations, RIL would have made profits of 50 per cent if it had supplied gas at 2.34 dollars. 

 

GOLD-PLATING CAPITAL

COSTS AND ROLE OF DGH

The gas and oil field in question is known as KG-DWN-98/3 (Block D-6), and consists of 8,100 sq km of offshore area in the Krishna Godavari basin. Block D-6 was awarded to Reliance Industries (90 per cent) and Niko Resources Ltd (10 per cent) under New Exploration Licensing Policy 1 (NELP-1) bidding round under a production sharing contract. Initially, the D6 was to produce 40 million MMSCD (million cubic metres per day), which was subsequently revised to 80 MMSCD. The initial development cost in the contract was 2.4 billion dollars which was revised through an “addendum” in 2006 to 5.2 billion dollars in the first phase and 3.3 billion dollars in the second phase. The CAG has also observed that the 3.3 billion dollars for the second phase has every possibility of being hiked up in the same way as the first phase.

 

The production sharing contract (PSC) that the government had struck with the RIL in 2000 envisaged that there would be something called “cost petroleum,” which would cover government royalty of 5 per cent, operating costs, the costs of exploration, and the development cost of producing gas. Till the  capital costs are recovered, 90 per cent of the petroleum/gas sold would be considered as “cost” petroleum and the rest 10 per cent would be “profit” petroleum.

 

The catch here is that the proportion of profit sharing changes depending on the amount of cost recovered to the total cost, something that the contract calls as investment multiplier. The proportion of shares between RIL and the government is pegged to this investment multiplier. Till the major portion of the costs is recovered, Reliance gets the major share of the “profit” petroleum. It is only after the major part of the costs have been recovered that the investment multiplier begins to increase and so does government’s share, which is pegged to this investment multiplier. That is why increasing capital costs helps Reliance retain a much larger share of the profits in the initial years, while the government gets its share only in the last phase, when the production starts to decline.

 

Reliance therefore can make a double killing --- by over-invoicing the capital costs, it can skim money from the top. In addition, by ensuring that the capital costs take a longer time to recover, it takes out its major share of the profit right in the beginning.

 

If it was only a question of getting money later, it could be argued that the government has not suffered a loss, only postponed its earnings. But here is the problem. In financial accounting, money earned later has to be discounted by an amount equivalent to what we would have earned if we had put the money in the bank and earned interest. The same amount earned today therefore is more valuable than money earned one or more years later. If we apply the  standard discounted cash flow method --- discount future earnings by a nominal discounting rate of 10 per cent --- we find (see table below) that the government’s share would have been 63 per cent of the total profits if the original figures of production and capital costs retained, while now it is only 48 per cent. Conversely, Reliance’s share goes up from 37 per cent to 52 per cent.

 

 

 

Capital Costs

$ Billion

Production Volume MMSCMD

Total Profits

$ Billion

RIL’s Share  per cent

Gov’s Share

 per cent

Discounted RIL Share

 per cent

Discounted Govt’s Share  per cent

Original

2.5

40

19.4

30

70

37

63

Revised

8.8

80

35.4

44

56

52

48

 

Notes: (1) Calculations done by the author. (2) Figures based on a 12 year production period and constant gas production. (3) If a 16 year period is taken and/or production figures increased, the figures would change somewhat, but the broad trends would remain the same.

 

SUSPICIOUS

DOUBLING

If we look at the fact that the extra investments have doubled production, how much has each of the parties gained out of this doubling of revenue? Out of the extra revenue (at discounted prices) of about 7.5 billion dollars, Reliance gains about $5.5 billion and the government only about 2 billion dollars.

 

The increase of four times the capital cost for a mere doubling of production had always seemed highly suspicious. No logic can explain why the doubling of capacity should lead to such an increase – economies of scale normally ensure that a doubling of capacity would increase capital cost by about one and a half times. The draft CAG report now makes clear that the increase from 2.4 billion dollars to 5.2 billion dollars took place for the first phase, where no augmentation of capacity was involved. This makes nonsense of the bidding procedure for awarding of blocks, as the calculations for award of blocks involves profit shares promised by the various parties. If the capital costs change, all this change, vitiating the award of contract itself.

 

Not only did the Directorate General of Hydrocarbons accept this increase in capital cost, which under the contract it need not have accepted; it did so in unseemly haste --- it took a scant 53 days to go through the cost increase of nearly 6.3 billion dollars. Some wizardry indeed!

 

The CAG’s draft report brings out the various ways costs could have been doctored --- single party bids, making changes to scope, substantial variation on orders, etc. the CAG has stated that it is going to examine these issues in greater detail in a subsequent audit. 

 

In November 2009, preliminary investigations by the CBI had found evidence of “gross abuse and misuse of public office” by V K Sibal, the then Director General of Hydrocarbons. This had been informed to the Petroleum Ministry and to the CVC. Numerous links had been found between Sibal and Reliance. The CBI enquiry remains stalled, very much in the telecom 2G mode, showing that Reliance tentacles in the government go far beyond Sibal.

 

CURIOUS CASE OF

4.2 DOLLARS GAS PRICE

An Empowered Group of Ministers (EGoM), in September 2007, set the price of gas at 4.2 dollars per MBTU for five years with no transparency and without giving any reason for this price. It might be noted that in the same period (2005-2008) the ONGC was being paid only 1.8 dollars per MBTU. The 4.2 dollars price was supposedly done on the basis of RIL’s price “discovery.”

 

The Reliance’s price discovery was to ask a selected set of bidders to quote a gas price according to a formula which fixed the price within a narrow range of 4.54 to 4.75 dollars. With this as the basis, Reliance declared the “discovered” price to be 4.59 dollars per MMBTU which was later revised to 4.3 dollars per MMBTU. The government then magnanimously decided that the right price was 4.2 dollars and claimed that it was arrived at through “a discovery” mechanism.

 

It might be argued that the government also gained out of the high price of gas. This is indeed true --- by our calculations, the Government stood to gain about 4 billion dollars or about Rs 20,000 crore from the increased price of gas as its share of profits. However, as gas is the major feedstock for fertiliser production and also a fuel for power, this gain has to be balanced against the resulting higher fertiliser and power prices. If the cost of production of fertiliser and power goes up, so does the government subsidy. So while the RIL would pocket the benefit of the higher cost of gas, the government would have to pay out a much higher subsidy of around Rs 75,000 crore for a gain of Rs 20,000 crore and therefore incur a net loss of more than Rs 55,000 crore.

 

It is indeed strange that at a time that the government complains about high cost of subsidies, it should itself promote policies that help private parties while pushing up its own subsidy bill.

 

Not only was the price set at a much higher level than the cost of production, it was also set in foreign exchange and pegged to the price of crude in the international market. Why should the gas price be set in dollars for even the future when the costs have already been incurred and therefore can easily be converted into rupees? Why should the gas price be set at 4.2 dollars when RIL itself admitted in the court proceedings between it and Anil Ambani’s RRNL/NTPC that its cost price of gas was 1.43 dollars and it was willing in 2004 to sell NTPC gas at 2.34 dollars? What is the justification of pegging the domestic gas price to the price of crude in the international market, to which it has no relation?

 

Fixing gas prices without examining cost figures and a mechanism of converting the cost figures to a gas price is making gas pricing another way of handing out private largesse. No basis of the gas price rate of 4.2 dollars has been given, so how did the ministers pull this figure of 4.2 dollars --- straight out of their collective hat?

 

PROMOTING RIL’S

MONOPOLY IN GAS

The last issue is one of monopoly. At the moment, Reliance is a major gas producer; Reliance Gas Transportation and Infrastructure Limited (RGTIL) owns the pipeline and again Reliance is getting orders for citywide distribution of gas. Unlike the electricity sector, the government does not have a problem in gas sector with a vertical monopoly of the type that Reliance is building. Originally, there was a proposal of a national gas grid, which would have the Gas Authority of India Ltd (GAIL) as the nodal agency. This also makes economic sense as whoever owns the gas grid effectively dictates to both the producers as well as the consumers. That is why generally such facilities are independently run, with the state playing a crucial role. Unfortunately, all such policies in the country come a cropper when Reliance is in the picture. So also with the original gas grid. If we have a gas grid now, it will largely be a Reliance grid, with the GAIL and others playing the second fiddle.

 

We are already seeing the effect of this monopoly, with the government owned GAIL becoming a junior partner to Reliance and the transportation cost of 1.25 dollars being charged by Reliance, over and above the 4.2 dollars and again without any regulatory oversight.

 

The CAG has made clear that the form of production sharing contract under the NELP is deeply flawed in favour of the private operators. It provides a perverse incentive to increase capital costs to the detriment of government’s share of revenue. This is a policy issue that needs to be urgently addressed in view of the large number of blocks that have been handed out under the NELP.

 

What does all this mean for the Indian people? Simply put, we are facing double loot. On the one hand, scarce national resources are being given away at a pittance. Gas and coal resources are being handed over to the Amabanis, Tatas and sundry others at throwaway prices. However, this is not helping the consumers, who are being asked to pay international oil and gas prices. Private loot of public resources coupled with public loot of the consumers --- this is the essence of our petroleum policies.

 

It is indeed welcome that the CAG has drawn attention to the problems in the production sharing contract under the new exploration policy of the government. However, it is important that other issues also be addressed, a key one being the pricing of gas. As for a CBI enquiry against officials who have connived with Reliance, public pressure will hopefully force a reluctant UPA to act. The only question is: Will the Reliance be also put in the dock for having subverted the government machinery and having secured these huge windfalls?