LITANY OF BROKEN PROMISES IN RAILWAY BUDGET 2011
HEAD |
PROMISES IN BUDGET 2010 |
COMMENTS |
WHAT WAS SAID IN BUDGET 2011 |
New Lines
|
1000 KMS IN 2010-11 |
25000 KMS in next 10 Years was Promised as part of Vision 2020 |
700 KMS to be Completed by March 2011 |
Upgradation of Stations |
94 Stations were declared as Adarsh Stations |
309 Stations were declared as Adarsh Stations in 2009 Budget |
442 Adarsh Stations to be completed by March 2011; 236 more Stations to Be made Adarsh Stations |
World Class Stations |
10 more Stations to be converted to World Class Stations |
50 Stations were selected for World Class Stations in 2009 Budget |
Not much headway because of ‘High Costs’ |
Multi-Functional Complexes (Shopping Centres, Restuarants, Stores, Pcos, Hotels, Multi-Level Parking etc. in Station premises) |
Construction of Another 93 MFCs to be taken up |
Construction of 50 MFCS by IRCON and RLDA was announced in 2009 Budget |
A few are in the ‘Process of Completion’; more MFCs announced |
Bottling Plants for Fresh Water |
6 Bottling Plants to be set up at Ambala, Amethi, Mal, Nasik, Farakka & Trivandrum |
Bottled Water was supposed to be provided at Stations at cheaper rates |
Not Mentioned |
New Ticket Centres |
Opening Ticket Centres at District Headquarters & Village Panchayats |
A promise to sell Computerized Tickets from 5000 Post Offices were made in Budget 2009 |
Not Mentioned |
Railway Safety |
anti-collission device (ACD) to be extended to 3 more zonal railways; 4 projects of train protection warning system (TPWS) covering 828 KMS will be implemented in 2010-11 |
Extension of ACD to South, South Central & South Western Railways was Announced in 2009 |
‘will be Commissioned’ in 3 Zones; to be Extended to 4 more zones; no mention of TPWS |
Unmanned Level Crossings |
Another 1000 level crossings will be manned in 2010-11 |
Manning of 3000 unmanned level crossings was approved in 2009-10 |
1500 unmanned crossings eliminated; 2500 unmanned crossings to be manned next year |
Sports |
5 Sports Academies to be set up at Delhi, Secunderabad, Chennai, Kolkata & Mumbai |
Astro-Turfs for the Development of Hockey was also promised |
Not Mentioned |
CULTURE & HERITAGE |
Rabindra Museum at Howrah; Gitanjali Museum at Bolpur to Commemorate 150th Anniversary of Tagore |
Shambhu Mitra Cultural Complex at Howrah was also promised |
Not Mentioned |
Housing |
“House for all” Railway Employees |
to be provided in 10 years |
Not Mentioned |
Hospitals & Educational Institutions |
522 hospitals and diagnostic centres (Including 40 multi-specialty hospitals), 50 Kendriya Vidyalayas, 10 Residential Schools |
Degree colleges, technical and management institutions also promised for children of railway employees |
Hospitals not mentioned; 20 medical road medical vans to be provided; RVPB to be set up to improve school quality; 20 hostels for children of railway employees have been commissioned |
Coach and loco factories |
New coach factories at Kancharapara and Palakkad; DMU factory at Sankrail; second unit at ICF Chennai; coach MLR workshop at Anara (Adra); loco factories at Medhepura & Marhora to progress |
Work on Rae Bareilly coach factory to ‘pick up’; willingness to set up coach factory at Singur also expressed |
First coach from Rae Bareilly to turn out within three months; all other projects are ‘progressing’ and a ‘core group of officers’ are working to ‘take them forward’ |
Wagon Factories |
5 Wagon factories at Secunderabad, Barddhaman, Bhubaneswar/Kalahandi, Guwahati and Haldia |
In JV/PPP mode |
‘Already executing works’ or ‘also to be taken up’ |
Rail Axle Factory |
New Rail Axle factory in new Jalpaiguri; two Poh/Ioh Workshops For High Axle Load Wagons in Maharashtra and Dankuni |
JV/PPP mode |
‘Taken up’ |
Kisan Vision Project |
6 Cargo centres for Perishable Agricultural products to be set up as Pilot Projects in Dankuni, Mechcheda, Nasik, new Jalpaiguri, new Azadpur & Singur; |
Refrigerated container factory in PPP mode in Budge also promised |
Mentioned once as being among policy initiatives which have received ‘encouraging’ response |
Auto Hubs |
Automobile and Ancillary Hubs at 10 Locations |
… |
Mentioned once as being among policy initiatives which have received ‘encouraging’ response |
Eco Parks |
10 Eco parks to conserve forest and wetlands under railways
|
… |
Not Mentioned |
Dedicated Freight Corridors |
DFCCIL to be revamped; land Acquisition without inconvenience to people; Sonnagar-Dankuni Section of Eastern Corridor Project to start during 2010-11; Preliminary study for remaining four corridors: North-South; East-West and South-South |
‘Diamond Corridor’ was announced in budget 2009 |
Main agreement with JICA signed for Western Corridor; Bidding Process has commenced; work ‘has started’ on Eastern Corridor in Dankuni |
Dedicated Passenger Corridors |
Golden Rail Corridor announced; 6 high speed passenger Rail Corridors of 250 to 350 KMPH speed |
national high speed rail authority to be set up |
Pre-feasibility study for Delhi-Mumbai leg to start ‘early next year’; objective to raise speed of passenger trains to 160-200 KMPH |
Trans Asia Railway Network |
Rail link between Akhaura in Bangladesh and Agartala in India |
As per agreement between the two Governments in January 2010 |
Not Mentioned |
Socially Desirable Rail Connectivity |
Surveys for 114 New Lines; 55 more New Line Surveys Considered as per Requests; 2 New Gauge Conversion Surveys; 7 Doubling Surveys; 5 Short Link Surveys |
5 new line surveys to Nepal also |
94 to be completed by March 2011; work to commence in 12th Five Year Plan (2012 onwards) under PMRVY |
If This is the Record vis-a-vis the Promises Made In 2010, can we Believe in the Promises made in 2011?