People's Democracy(Weekly Organ of the Communist Party of India (Marxist) |
Vol. XXXII
No.
27 July 13 , 2008 |
WITHOUT
COMMENT
WHO ARE RESPONSIBLE FOR
SLOWING DOWN OF NUCLEAR
POWER PROGRAMME?
23rd
report of Parliamentary Standing Committee on Energy on Demand for
Grants of
the Department of Atomic Energy for the year 1995-96
THE
Department of Atomic Energy in 1984 had set for itself a target of
10,000 MW of
nuclear power capacity by the turn of the century. To meet the
requirements in
this regard advance action was taken after all cabinet approvals had
been
granted. Consequently for procuring
various items indigenously orders were also placed it, however, appears
that
the programme has since been abandoned (emphasis
added). The present programme is to achieve a total nuclear installed
generating capacity of 2820 MW by the year 1997. The
Committee feel that this abandoning of
the action plan had many adverse consequences. A great deal of damage
has been
done to our indigenous effort and to the industry. The Committee are of
the
view that a complete explanation on this matter is owed by the
government. The Committee�s views about
Nuclear Power, as
an answer to our power shortage have been explicitly stated may times. The Committee, therefore, while demanding such
an explanation recommend that adequate, and needed budgetary support
must be
provided to meet the requirements of nuclear power programmes of the
DAE.
The nuclear power
profile
of the Department formulated in 1984 projected an installed capacity of
10,000
MW by 2000 A.D. When the profile was
approved in principle in 1985, by the government of
With a view to
mobilise
adequate resources for the power programme, the Nuclear Power
Corporation of
India Ltd. (NPCIL) was formed in September, 1987. It was excepted that
extra
budgetary resources would also be raised which would accelerate the
nuclear
power programme. At the time of
formation of the Corporation it was agreed that the funding of future
projects
including works in progress and interest during construction would be
in the
form of 50 per cent as government equity and 50 per cent as loan. The equity portion of budgetary support
amounting to 50 per cent of the Project cost was to be released first
and
utilized. However, due to financial
constraints the Government could not adhere to this commitment. The NPCIL since its inception ahs mobilized
Rs.2883 crores from the market through Bonds to support the nuclear
power
programme. As the resource crunch became
more acute the Corporation had difficulties in further resources
mobilization
from the market and the Department had to reduce the target.
The principled
stand taken
by
As the budgetary
support by
government is being reduced from year to year and the inability of the
Corporation to raise adequate Extra Budgetary Resources from the open
market
coupled with the problems mentioned above, the targets set earlier
could not be
achieved by the year 2000. Increase in
contribution in power generation will emerge only with the availability
of
adequate resource in the coming years.
The Planning Commission, have, however, indicated that all out
efforts
will continue to be made to augment the budgetary support to the extent
possible
within the overall resources constraints.
Comments
of the Committee
�.
Not accepted
The Committee
have in a
separate report dealt with the adverse implications of abandoning the
Nuclear
Power Programme formulated earlier. The Committee would, however,
reiterate
that adequate and needed budgetary support must be provided to meet the
requirements of Nuclear Programme of the DAE.