People's Democracy(Weekly Organ of the Communist Party of India (Marxist) |
Vol.
XXIX
No. 25 June 19, 2005 |
What
Will Enron Power Really Cost?
More
Enron, Less Electricity?
THE month of May 2005 has witnessed a series of significant events taking place in the electricity sector of the state of Maharashtra. Throughout April, sweltering heat coinciding with widespread loadshedding and a peak load deficit of 3000 MW. Growing public discontent about power cuts, set the backdrop for what appears to be well-coordinated actions by the Shiv Sena- BJP along with the NCP, which is a constituent of the ruling alliance, and also holds the state’s power ministry.
On
the eve of May Day, which is also celebrated as Maharashtra Day in the state,
NCP chief and Union cabinet minister Shri Sharad Pawar, triggered the process
with his statement that it was a major mistake for the government to have
accepted the report of the Godbole committee on Maharashtra’s power sector and
the Dabhol project, and that the state’s present power shortage was due to
that incorrect decision. The very next day, Maharashtra Day, saw mobs led by the
Shiv Sena attacking offices of the Maharashtra State Electricity Board at Pune,
with BJP taking the lead at Akola, assaulting the employees and destroying
public property.
For
the next few days newspapers known for their closeness to Pawar, Shiv Sena
BJP, and big business dailies carried front page stories about the power crisis
in the state and the problems being caused by loadshedding. Statements by NCP,
Shiv Sena and BJP state leaders were projected prominently. This media campaign
had a common theme: that it was a big mistake to stop the Enron project, that
the present power shortage was the result of that incorrect decision by the
Congress government taken under pressure from the Left, and that reviving Enron
was now necessary to rescue Maharashtra from its power crisis.
Towards
the end of May, the BJP took to the streets throughout the state, on the issue
of power cuts, attacking MSEB offices and holding rasta rokos, damaging
state transport buses with stone throwing. The Maharashtra chief minister came
out with the admission that of the 1210 MW of extra power promised to
Maharashtra by the prime minister from the national grid, 600 MW was practically
unavailable because, being naphta based, it was too expensive and the MSEB could
not afford to purchase it.
Four
years earlier, the unaffordability of expensive naphta based power had led to a
financial crisis in the state, disputes between MSEB and the Dabhol Power
Company, and the shutdown of the Dabhol project, which has remained shut ever
since.
It
may be recalled that when the project had been earlier cancelled and then
renegotiated by the Shiv Sena- BJP government in 1995, power from Phase 1 was
promised to be made available at a renegotiated levellised tariff of Rs 1.89 per
unit. The actual tariff during each month of the 25 months supply of Phase 1
Enron power is shown in the following chart:
DABHOL POWER COMPANY MONTHWISE TARIFF
(May 1999-May 2001)
|
April |
May |
June |
July |
Aug |
Sept |
Oct |
Nov |
Dec |
Jan |
Feb |
Mar |
1999-2000 |
|
3.79 |
4.85 |
4.49 |
3.02 |
3.46 |
5.71 |
3.83 |
4.35 |
5.12 |
4.44 |
5.23 |
2000-01 |
4.36 |
3.48 |
25.50 |
7.80 |
6.80 |
5.10 |
6.90 |
8.00 |
8.53 |
20.90 |
14.46 |
8.55 |
2001-02 |
10.22 |
8.75 |
|
|
|
|
|
|
|
|
|
|
(Source:
Affidavit filed by MSEB before Kurdukar Commission)
Far
from the promised Rs 1.89 per unit, during the last one year of supply the
average tariff was more than four times that figure.
ENRON REVIVAL PLANS
In the light of the above events, it came as no surprise when, on May 9, an announcement was made of the imminent revival of the Enron project, with power being made available at Rs 2.30 per unit to Maharashtra, at 80 per cent plant load factor. This announcement, from the high powered committee set up for this purpose, of which Shri Sharad Pawar is a member, also mentioned that further investments of several thousands crore rupees would be necessary to restart the project, including a settlement payout of between Rs 1276 crore and Rs 1452 crore to GE-Bechtel. Additional Payouts to OPIC and foreign lenders would be of the same order. Completion costs of the project would add another Rs 880 crore on a preliminary estimate. Additionally there would be the costs of completing and commissioning the regassification LNG terminal, which would be undertaken separately by GAIL.
Given
the track record of unrealistic tariff claims made in the context of the Dabhol
project, and the extremely serious consequences of such fraudulent claims,it
would be prudent, to say the least, to subject the above claim of a Rs 2.30 per
unit tariff to a reality check.
REAL
COST
Electricity
tariff consist of two parts: A fixed cost (capacity charge) which is based on
the recovery of the capital invested of the project, and an energy variable cost
based on the costs of fuel. Since the capacity charge depends on the ultimate
costs of the project, a precise calculation will have to await more transparency
on the various heads mentioned above. However, based on available figures and
reasonable estimates of what is still unclear, a calculation of the actual cost
of power from a revived Enron project has been made by power engineer and
retired director of Indira Gandhi Centre for Atomic Research, Kalpakkam, which
arrives at an estimate that at today’s costs, Enron power would cost at least
Rs 3.29 per unit, a rupee more than the announced price of Rs 2.30 per unit.
According
to the detailed calculation made by Shri Paranjpe, fixed costs would amount to
Rs 1.27 per unit at 80 per cent PLF. Energy costs would depend on the price of
LNG imports. In 2001 the Godbole Committee cited a cost of 2.8 per million
dollar BTU, when crude oil was at 24 dollar a barrel. Assuming a cost of 5 per
million dollar BTU with oil at 50 dollar a barrel currently, translating into a
cost of 6 dollar per MBTU after regassification, the variable energy cost works
out to Rs 2.02 per unit. The electricity tariff of a revived Enron project thus
works out to Rs 3.29 per unit, even assuming no further increase in the price of
imported hydrocarbons, in the intervening period.
The
additional rupee per unit translates to an additional payout of Rs 1530 crores
per year at 80 per cent PLF for the 2184 MW Dabhol plant. At Rs 3.29 per unit,
Enron power at 80 per cent PLF would cost over Rs 5000 crore per year. Can
Maharashtra’s power sector cope with this financial load?
Electricity
and financial flows have many things in common. If supply does not match demand,
both electric and financial circuits can trip and shutdown. If power grids can
collapse, so too can power markets fail, leading to power cuts. Because
electricity is such an essential service, it was assumed by the proponents of
liberalisation and privatisation in the power sector, that there would always be
demand for power, no matter what the cost. The reigning catchword of the
nineties was “No power is more expensive than no power”, and hence that cost
did not matter.
It
has not take long for reality to trip these illusions. It was power market
failure that led to the collapse of Dabhol Phase 1. Power markets have
systematically failed and continue to fail in Orissa and other states, a fact
which is sought to be concealed by pumping huge subsidies in the form of loans
to stave off bankruptcy of the privatised power companies, so that the larger
World Bank power privatisation project does not get scuttled nationally.
With
only 50 per cent of MSEB’s electric supply being metered, where will the
additional Rs 5000 crore revenue be realised to pay for Enron power is a
question that needs to be clearly answered. All official reports in recent years
have clearly stated that high tension industrial consumers cannot pay more than
the current tariffs. Raising HT tariffs would lead to an exodus of industry from
the state, or a shift to captive power plant supply. With agricultural consumers
unable to pay even the highly subsidised tariffs of today, whether domestic and
commercial consumers can sustain the Enron financial load is a question that
must be considered before committing several thousand crore rupees of further
investments.
MORE
ENRON LESS
ELECTRICITY
In
1993, the World Bank had twice reiterated that as a base load plant an LNG based
plant of 2000 MW size was not viable. Thereafter the Rajadhyaksha Committee had
raised similar doubts about the economic viability of the three IPP projects
being planned for Maharashtra, including Dabhol. In 2001 the Godbole Committee
stated unequivocally that “LNG is
not a cost effective solution to meet base load power”. With hydrocarbon costs
rising steadily it would be prime folly to proceed
without a proper technoeconomic reappraisal of the viability and
sustainability of a revived Enron project, which must be insisted upon before
any further commitments are made.
If
Enron power is indeed being made available to MSEB at Rs 2.30 per unit, then who
is footing the Rs 1500 crore subsidy is another important question. If NTPC is
bearing the subsidy, it must be noted that a financial burden of this size can
bankrupt even a large healthy PSU like NTPC, to the detriment of the nation.
Alternately, if the burden is distributed over the total electric supply from
NTPC, so as to camouflage its origin, the resultant tariff increase
nationwide is likely to be challenged in the CERC and lead to a major
dispute between states.
If
the high power committee which has been formed to revive the project is
considering any of the above issues, there are no public indications of this. On
the contrary, the public pronouncements of this committee show the same
tendencies of disinformation and making of dubious claims, which have
characterised the project over the past decade, with catastrophic consequences.
Problems will not go away because they are not looked at. If Phase 1 collapsed
because of payment default, the chances of something similar happening on a
larger scale with Phase 2 are high and cannot be wished away. Should this
situation arise in future, and payments committed to Enron pushed through,
regardless, default on the other, less insulated, payments for power purchase
would lead to the other supplies being shut off. With finite amounts being
available for power purchase in the state, more Enron may actually mean less
electricity for the state of Maharashtra.
The
issues of electricity and load shedding, the fate of MSEB and Enron are set to
dominate political scene in the coming months. The NCP has joined hands with the
Shiv Sena and BJP in this ground alliance. Their nexus in electricity and Enron
matters is a long standing one, so much so that the three parties are known in
Maharashtra as the Enron Mitra Mandal. They joined hands to bring Enron, and
equally unviable IPPs to Maharashtra. To this end they have ensured that the
power ministry in the State has remained in their hands for more than a decade,
which position they have used to systematically block growth of public sector
generation, so as to create shortage conditions in which expensive private power
can be hustled through. At the centre too, it was no accident that during the
NDA government, Suresh Prabhu and Anant Gite of the Shiv Sena, and Jaywantibai
Mehta of the BJP between them held the power ministry. The same nexus was seen
in their successful attempts to stall the Kurdukar Commission which had started
investigating the Enron debacle. An important political task of the democratic
forces in Maharashtra, is to expose this unholy nexus before the masses, and
build public awareness about their complete responsibility for the state’s
current power shortage, which situation they now seek to exploit to revive their
broader failed agenda.
There
are many important issues being thrown up by the power shortage in Maharashtra-
the responsibility for this crisis, the fate of MSEB and public sector power,
the sustainability of current power policy based on privatisation, and feasible
alternatives available. It is not possible to discuss these issues within the
scope of this article, and they will be taken up separately later. Even with
regard to Enron there are a number of critical issues like jurisdiction of
Indian and international law which have recently come to the forefront, huge
claims made in arbitration against the country by GE-Bechtel, which we do not
discuss at this point. There is no doubt that the Enron project is one of the
world’s biggest and most expensive fiascos. Issues of misgovernance and undue
influence at every stage have been squarely raised by a number of official
reports. In the USA Enron Chairman Kenneth Lay was arrested and shown in
handcuffs on BBC and CNN. Enron CEO Jeff Skillings and many other top officers
have also been criminally indicted. In India, on the other hand, not a single
person has been called to account till date.
RECONSTITUTE
COMMITTEE
In the light of the events of May, it has become imperative to demand an immediate reconstitution of the high power committee which is considering Enron. When the committee was formed, the financer minister Shri P Chidambaram excused himself from the committee on the grounds that he had appeared for Enron as an advocate in legal proceedings. Given the objection to Kurdukar Commission by Shri Sharad Pawar, which is on the record, and his recent conduct vis-a-vis the Godbole Committee report, an official report accepted by his own government, it is wholly inappropriate that he be part of any Enron renegotiations. In fact it is wholly inappropriate and a conflict if interest that any person who was party to creating the Enron mess in the first place, including Shri Montek Singh Ahluwalia, should continue in such a committee. Such persons have been collectively indicted by the Godbole Committee, and there is material on record before the Kurdukar Commission to assign personal responsibility for various irregular acts. The events of May demand a reconstitution of the High Power Committee and also the re-appointment of Kurdukar Commission by the Central government to circumvent issues of centre-state jurisdiction which were used to stall the Commission. (June 4, 2005)