People's Democracy(Weekly Organ of the Communist Party of India (Marxist) |
Vol.
XXVI No. 02 January 13,2002 |
Andhras IPP Policy: Private Loot of Public Finances
Prabir Purkayastha
ANDHRA PRADESH has recently signed a Memorandum of Agreement (MoA) with a set of Financial Institutions (FIs), primarily Power Finance Corporation (PFC) and Industrial Development Bank of India (IDBI), so that that these FIs can finance six Independent Power Producer (IPP) projects in Andhra. Andhra and the central governments have claimed these steps as a great innovation in power sector reforms.
Before we go into the salient points of the Agreement, it is necessary to see why such an agreement is necessary at all. The prime objective that the IPPs were supposed to have fulfilled bringing in additional capital to reduce the burden on public finances -- never happened. The proposal to induct private capital in the power sector was to allegedly address the lack of resources for public investment in power projects. The Gazette of India notification issued by the ministry of power in 1991 stated "With the objective of bringing in additionality of resources for the capacity addition programme in the electricity sector, government has formulated a policy to encourage greater participation by privately owned enterprises in the electricity generation, supply and distribution field". The IPPs however, brought in very little capital but have all "borrowed" public funds for most of the capital costs of their projects.
UNVIABLE IPPS
Dabhol Project, for example, saw Enron "borrowing" 1.2 billion dollars from Indians FIs who also guaranteed another 700 million dollars borrowed by Enron from foreign lenders. The Maheshwar Project of S Kumar is being provided 90 per cent of its funds from FIs, the public sector and the MP government. The Spectrum Godavari case (see Box) has shown how the promoters have taken public money loans from FIs -- and re-circulated a part of it through the turnkey contractor, Rolls Royce, and brought it in as their "equity". The net result of these shenanigans has been high plant costs and expensive power to the consumers. With such high costs, the IPPs are becoming increasingly unviable, and the FIs are faced with their loans turning into Non Performing Assets (NPAs). The Dabhol case alone will see NPA due to one IPP of the order of Rs 9,000 to 12,000 crore.
It is in the context that we have to see the existing and future IPP projects. Even after the Dabhol fiasco, the FIs have learnt nothing. Nor has the government. This is why they are trying to push this bankrupt IPP mode of power development in Andhra. As public outcry has made it difficult to raise tariffs continuously, the IPPs need guarantees to borrow money for their projects. If they can borrow enough funds, they would take out their equity plus profits by recycling it through their contractors in the same way as in Spectrum or in Dabhol. They would then "own" these plants as well have made a tidy sum even before a kilowatt is produced. If the project becomes sick like Dabhol, the FIs, will be left holding the bag. Only their money public money will be at stake. If the state government and the Regulator agrees to the high price of IPP power, the "owners" will continue to rake in the moolah without spending a single paise of their money towards equity.
The important issue here is the bankability of the projects. None of the "owners" are willing to mortgage any of their assets for taking loans. They have argued that AP Transco must take the entire risk of the project and give suitable guarantees to the lenders. The above MoA signed between FIs, AP Transco and the Andhra Pradesh government has done precisely that.
AP TRANSCO TO BEAR RISKS
Let us forget all the cosmetic measures that have been promised, such as 100 per cent Metering, Energy Audit, reduction of T&D losses etc. These are measures that need to be taken in any case whether there is an IPP policy or not. The operative part of the agreement relevant to the IPP policy is that AP Transco is going to mortgage its assets to the FIs for loans that will be taken by the IPPs. If this is not enough Transco has also agreed to hypothecate all its present and future receivables till it opens an "escrow" account. This "escrow" account will be such that the IPPs will have the first charge on the money that will be received by AP Transco. In other words, all the risks of the IPP projects are being guaranteed by the state owned AP Transco.
Incidentally, after restructuring of the erstwhile AP State Electricity Board, there are a number of distributors that have been hiked off which are slated for privatisation. The transmission system is with the state owned AP Transco, who will buy power from the generators and sell it to the distributors. The generators, who are also to be privatised, will sell power, not directly to the distributors but to Transco. The question here is a very simple one. If the FIs are giving the money on the basis of AP Transcos guarantees, why should the IPPs own the projects? Textbook capitalism tells us capitalists get profits as they take risks. Apparently, this is not true for capitalists in India and certainly not in the power sector. Gone also is the argument that IPPs bring in additionality of resources.
PRIVATE APPROPRIATION OF PUBLIC CAPITAL
It is now clear what is going on in the power sector reforms; it is private loot of public capital. FIs are simply bankrolling private capital. This is what we have seen in the UTI scam as the Tarapore Committee Report makes clear. And this pattern is continuing in the power sector with money coming to private coffers from PFC, IDBI and IFCI.
It is bad enough that the entire MoA is geared to forcing AP Transco to carry all the risks of IPPs. Even worse, is that the projects proposed are themselves viable. Whether the risk is borne by AP Transco or the FIs, the six IPP projects (given in table below) are likely to sink even if the project costs are not unduly inflated.
Sr. No. | Proposed IPP | MW |
1. | Ramagundan Extn (BPL Group) | 520 MW |
2. | Konassema Oak Well Power Ltd | 445 MW |
3. | Vemagiri CCGT (Ispat Power LTd) | 370 MW |
4. | NCC-Gautami Consortium | 464 MW |
5. | BSES Andhra Power Ltd | 220 W |
6. | Jegurupada II (GVK Industries) | 220 MW |
Total | 2,239 MW |
In the above 2,239 MW of IPP capacity, only 520 MW Ramagundan plant -- is coal based. The rest 1719 MW is naphtha or gas based. As there is not enough gas to support these projects over and above what has already been implemented: Vijjeswaran, Jegurupadu I, Lanco Kandapalli and Spectrum Godavari Projects. In the absence of gas, these projects will be largely liquid fuel based.
This brings up the next question. If there is not enough gas, why is the AP government pursuing the hydrocarbon fuel route? Once these projects go on-stream and we see that there is not enough gas, then the true cost of IPP power will become clear. It is in order to hide this reality that the Andhra government is talking about there being enough gas for all these projects. There may be gas, but only in Chandra Babu Naidus imagination unfortunately this gas does not burn and cannot produce any power.
IPP POLICY A BIG SCAM
The IPP policy and the so-called MoA and facilitation agreements are emerging clearly as another big scam. Already the existing IPP projects have pushed up the rate of power in Andhra sky high. With naphtha as fuel for the new projects, the entire power sector in Andhra will turn sick. For those who are signing these agreements and the IPP promoters, it may matter very little as they are more concerned about sanctioning projects and securing loans rather than making these projects successful. The promoters will have made their money; those who hold the reigns of power in the state today, will mostly probably have been consigned by then to the rubbish bin by the people of AP. However, the Indian people, whose money the FIs are gifting lavishly to the IPPs and the people of Andhra, who will be left with a bankrupt power sector, will have to pay a very heavy price for these misdeeds.